Data center load bank

Loadbank for test and evaluate the cooling system and power capacity of the data center

Loadbank for Data Center is a solution to check the safety of equipment placed in the data center room, Scada room before acceptance for operation, Data center loadbanks manufactured by Vietpro also allow use for testing. Routine maintenance avoids unfortunate risks caused by abnormal conditions in the data room such as CRAHs not being able to maintain room temperature after a short period of operation, or due to unstable power supply. fixed, burning contacts of sockets, connection contacts…

Vì sao phải kiểm tra Data Center bằng tải giả
Loadbank rack type is usualy use for Data center

So how does a dedicated loadbank help test the true capacity of Data Centers?

Solution using heat loadbank to test real capacity for Data Center - Vietpro

1. Loadbank allows testing the maintenance of server room temperature when running at 25%, 50% and 100% power levels (Full load) or flexible options at other power levels. as required. Specifically, testing the circulating refrigeration equipment in CRAHs, testing the cooling capacity of industrial air conditioning systems…

2. The loadbank heat loads produced by Vietpro also allow to simultaneously test the capacity of the main power supply at normal levels of 25%, 50% and 100% full load for the supplies. power supply at 200kW, 500kW, 1MW or at higher power levels up to 5MW…

3. Loadbank AC is also used to check standby generator rated power test at different power levels at 25%, 50% and 100% full load as well as over withstand test load, within the time allowed as declared by the manufacturer

tải giả 2kW cho Data Center
Loadbank Vietpro rack mount design

4. Loadbank also allows to test the rated capacity of the standby UPS/Converter at power levels when running at 25%, 50% and 100% capacity as well as to test the overload tolerance for a period of time. allowable time as declared by the manufacturer

5. Using electric load loads to check connection contacts, electrical sockets according to electrical standards to ensure safety against fire, explosion…

6. Data center also requires the use of dummy DC load with voltage levels 110VDC, 220VDC, 420VDC… with discharge current levels from 200A to 4,000A for battery banks to check and measure capacity UPS battery capacity, DC power reserve from 500AH to 6,500AH

Testing the future load capacity is a must in case the data center server equipment will be installed to upgrade the capacity to maximum 100% (Full load) in accordance with the equipment. Initial designs in simulated situations are given. When the system is running stably, or a situation where 100% of the servers also start up at the same time, causing a huge increase in current and cold room temperature, it can be tested using a dedicated dummy load with a capacity of 2,000W. VPR P220ABE2000D or use can use ant loadbank with a capacity of up to 4kW greater than as VPR P220ABE4000D… Note that data centers always require the use of loadbank (dummy loads) to test the capacity and cooling capacity of the device. server room before being put into use with a rather long inspection time from 30 to 90 days continuously…